Project Management #3

  1. 1) Following are cost and schedule data for a project that is underway.

  1. a) Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs
  2. b) Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance
  3. c) Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?